Blundell Geothermal Rock Muffler
























































This project is located northeast of Milford, UT. It is a patented design by Veizades Associates out of San Francisco to control the pressure released when the plant shuts down. Dailey Builders constructed the walls and floor and we did the Base slab and installation of baffles.

Willow Beach Recreation Area











The Maintenance building is completed and a good portion of the Concession building footings and walls are now complete.

Wednesday, October 28, 2009

3 Peaks Substation - Control House & Transformer Pad











M.S. poured the footings and flatwork and Allred and Allred setup the walls. This was not the typical job as it was for the main controls of a substation. Many wall penetrations and embeds were installed to facilitate all the wiring.